Kravis Center

701 Okeechobee Boulevard
West Palm Beach FL 33401

Four (4) baseman machine traction elevators car group – 4.500 Lbs – 350 fpm – 6 Landings

Full Modernization, DC generators to ACVVVF drive conversion, new non-proprietary controllers, door equipment, cab renovation, fixtures, and wiring. Special service elevator selective operation.

Three (3) hydraulic elevator full modernization
Car Group – 2.500 Lbs – 150 fpm – 5 Landings

New Installation
One (1) MSA “Machine side adjacent” Traction Gearless Permanent Magnet machine – 2.500 Lbs – 200 fpm – 4 Landings

Kravis Center

A&A Elevator Recent Projects

Bank of America

Traction elevator modernization 4601 Sheridan Street, Hollywood, FL 33012

Two Duplex operation traction elevators 2.500 lbs. – 250 fpm – 6 Landings.

Complete modernization including replacement of controllers, conversion from DC generators to AC VVVF drive, door equipment, fixtures, cabs, etc.

Brickell Townhouse Condo

2451 Brickell Avenue
Miami, FL, 33129

Four (4) car group DC traction Elevators Gearless Machines – 2000 Lbs – 500 fpm – 21 Landings

Complete modernization including replacement of controllers, refurbish existing machine, door equipment, fixtures, cabs, etc.

Fountainblue Garden

8185 NW 7th St, Miami

2500 Lbs – 150 fpm – 5 Landings
ECC Pixel Control System hydraulic elevator full modernization.

Gables One – Miami University

1535 Levante Ave. Coral Gables, FL 33146

Five traction elevator car group – 3.500 and 4.500lbs. – 350 fpm – 13 Landings

Full Modernization, DC generators to ACVVVF drive conversion, new non-proprietary controllers, door equipment, cab renovation, fixtures, and wiring. Special service elevator selective operation.

Total job completion in 18 weeks while keeping 3 elevators running at all times for customer use, and avoiding interruption of normal building operation to the University.

Martinique II

4000 North Ocean Drive
Riviera Beach, FL 33404

4 Traction cars – 2 Duplex
3500 lbs. – 350 fpm – 25 Landings
Full Modernization, conversion from old DC generators to state of the art AC VVVF drive system, replacing traction machines, controllers, door equipment, fixtures, electrical components, cab, and doors renovation.

Job completion, 8 weeks for each elevator.

1 Hydraulic 2.500lbs. – 200 fpm – 5 Landings
Modernization, replacement of controller, power unit, door equipment, fixtures, electrical components, cab, and door renovation.

Installation of double bottom jack casing to comply with actual elevator codes.