A&A Elevator Recent Projects
Kravis Center
701 Okeechobee Boulevard
West Palm Beach FL 33401
Four (4) baseman machine traction elevators car group – 4.500 Lbs – 350 fpm – 6 Landings
Full Modernization, DC generators to ACVVVF drive conversion, new non-proprietary controllers, door equipment, cab renovation, fixtures, and wiring. Special service elevator selective operation.
Three (3) hydraulic elevator full modernization
Car Group – 2.500 Lbs – 150 fpm – 5 Landings
New Installation
One (1) MSA “Machine side adjacent” Traction Gearless Permanent Magnet machine – 2.500 Lbs – 200 fpm – 4 Landings
Sunrise lakes Phase 2
8120 Sunrise lakes Blvd
Sunrise Lakes, FL 33322
25 Hydraulics cars
2200 lbs. – 120 fpm – 3 Landings
Full Modernization and Cab decoration
Brickell Townhouse Condo
2451 Brickell Avenue
Miami, FL, 33129
Four (4) car group DC traction Elevators Gearless Machines – 2000 Lbs – 500 fpm – 21 Landings
Complete modernization including replacement of controllers, refurbish existing machine, door equipment, fixtures, cabs, etc.
Fountainblue Garden
8185 NW 7th St, Miami
2500 Lbs – 150 fpm – 5 Landings
ECC Pixel Control System hydraulic elevator full modernization.
Gables One – Miami University
1535 Levante Ave. Coral Gables, FL 33146
Five traction elevator car group – 3.500 and 4.500lbs. – 350 fpm – 13 Landings
Full Modernization, DC generators to ACVVVF drive conversion, new non-proprietary controllers, door equipment, cab renovation, fixtures, and wiring. Special service elevator selective operation.
Total job completion in 18 weeks while keeping 3 elevators running at all times for customer use, and avoiding interruption of normal building operation to the University.
Martinique II
4000 North Ocean Drive
Riviera Beach, FL 33404
4 Traction cars – 2 Duplex
3500 lbs. – 350 fpm – 25 Landings
Full Modernization, conversion from old DC generators to state of the art AC VVVF drive system, replacing traction machines, controllers, door equipment, fixtures, electrical components, cab, and doors renovation.
Job completion, 8 weeks for each elevator.
1 Hydraulic 2.500lbs. – 200 fpm – 5 Landings
Modernization, replacement of controller, power unit, door equipment, fixtures, electrical components, cab, and door renovation.
Installation of double bottom jack casing to comply with actual elevator codes.